Scope Control Is Everything
Telecom projects have a well-known tendency to expand — a fiber route that seemed straightforward turns into a permitting odyssey, a tower installation discovers structural issues requiring unexpected work, a network upgrade reveals outdated equipment that needs replacement first.
Aggressive scope management from day one is the only defense. This means detailed scoping in the design phase, contractual change order processes that are actually followed, and stakeholders who understand that scope changes cost money.
The Supply Chain Is Your Critical Path
Equipment lead times for telecommunications hardware — especially after supply chain disruptions — can be 6-18 months. Any project that starts procurement late will be late. We build supply chain milestones as the first critical path items in every project schedule.
Remote Project Logistics
For remote projects in Alaska, Hawaii, or other difficult access areas:
- Over-build your material list — you cannot make a quick trip to the supply house
- Plan for weather windows and have contingency crews identified
- Understand charter aviation and marine freight lead times
- Build 20-30% schedule contingency for remote work
The most expensive words in remote telecom project management: "We forgot to bring..."